Question: 1 / 400

After creating sprint backlogs, what is the next step for a project administrator in Scrum?

Review project requirements

Initiate sprint execution

Initiating sprint execution is the logical next step after creating sprint backlogs in a Scrum framework. Once the sprint backlog is established, which consists of the tasks and user stories that the team commits to completing during the Sprint, the focus shifts to actively working on those items. In Scrum, the sprint represents a deep focus period, typically lasting two to four weeks, during which the team works collaboratively to accomplish the goals set out in the backlog.

This step involves team members engaging in the work defined in the backlog, collaborating on tasks, and holding themselves accountable for meeting the objectives of the sprint. The sprint should start with a Sprint Planning Meeting, where the team discusses the tasks, assigns responsibilities, and strategizes their approach.

Other actions like reviewing project requirements, gathering team feedback, or scheduling a team meeting are important but come either before the sprint backlog creation or during the sprint as part of regular reviews and daily stand-ups. However, they do not directly follow the creation of the sprint backlog as the natural next step to drive the project forward.

Get further explanation with Examzify DeepDiveBeta

Gather team feedback

Schedule a team meeting